MEASURE OF DAMAGES
The measure of damages is the amount which will put the claimant
in the position he would have been in had the contract been properly performed.
This is sometimes called the ‘expectation
loss’ basis. In Victoria Laundry v Newman Industries, for example, Victoria
Laundry were claiming for the profits they would have made ( or the profits
they expected to make) had the boiler been installed on the contractually
agreed date. If there is no actual loss, the claimant can recover only nominal
damages.
Alternatively, a claimant may prefer to frame his claim in the
alternative on the ‘reliance loss’
basis and thereby recover expenses incurred in anticipation of performance and
wasted as a result of the breach. The onus is on the defendant to show that the
expenditure would not have been recovered if the contract had been performed.
Illustration: In a contract for the sale
of goods, the statutory (Sale of Goods Act 1979) measure of damages is the
difference between the market price at the date of the breach and the contract
price, so that only nominal damages will be awarded to a claimant buyer or
claimant seller if the price at the date of breach was respectively less or
more than the contract price.
In general, damages are not awarded for non-pecuniary loss such as
mental distress and loss of enjoyment. Exceptionally, however, damages are
awarded for such losses where the contract’s purpose is to promote happiness or
enjoyment, as is the situation with contracts for holidays – Jarvis
v Swan Tours.
The innocent party must take reasonable steps to mitigate
(minimise) his loss, for example, by trying to find an alternative method of
performance of the contract: Brace v Calder.
Liquidated damages clauses and penalty clauses
Liquidated damages can be defined as a fixed or ascertainable sum agreed
by the parties at the time of contracting, payable in the event of a breach,
for example, an amount payable per day for failure to complete a building. Such
clauses are called liquidated damages clauses.
If a contract includes a
provision that, on a breach of contract, damages of a certain amount or
calculable at a certain rate will be payable, the courts will normally accept
the relevant figure as a measure of damages.
The courts will uphold a liquidated damages clause even if that
means that the injured party receives less (or more as the case may be) than
his actual loss arising on the breach. This is because the clause setting out
the damages constitutes one of the agreed contractual terms.
However, a court will ignore a figure for damages put in a
contract if it is classed as a penalty
clause – that is, a sum which is not a genuine pre-estimate of the expected
loss on breach.
The law imposes a duty on the innocent party to take all
reasonable steps to mitigate his/her loss. If the innocent party fails to mitigate his/her loss, then the award of
damages will be reduced. The burden of proof is on the defendant to show that
the claimant failed to take reasonable opportunity of mitigation.
No comments:
Post a Comment